MINUTES

LITCHFIELD SCHOOL BUILDING COMMITTEE

 LITCHFIELD INTERMEDIATE MUSIC ROOM

JULY 15, 2004

 

 

A meeting of the Litchfield School Building Committee was held on Thursday, July 15, 2004, at 7:00 p.m. in the Litchfield Intermediate Music Room.

 

Present were: Jack Healy, Chairman; Robert Blazek; Mac Bramley; Stacey Kavle; Gary Waugh; Lynn Chapman; John Mullen; Kent Gilyard and Jeff Zullo

 

Also Present: John Tindall-Gibson; Peg Perusse; Tim Breslin; Anne Stillman; Richard Munday, Tim Callahan, Fernando Pastur; Ryan Minney of Herbert S. Newman Partners; BOE Members, Wayne Shuhi, Don Falcetti and Frank Simone;  Greg Oneglia and Bruce Walpole of O&G Industries; BOS Member Bill Dranginis; Public and the Press.

 

Meeting was called to order at 7:03 PM by J. Healy

 

Approval of Minutes

 

Motion was made by M. Bramley to approve the Minutes of the meeting of July 1, 2004, seconded by K. Gilyard.

Motion Carried.  All votes were in the affirmative.  Lynn Chapman abstained.

 

Motion was made by M. Bramley to move item 4. Communication before item 3. Public

 Participation, seconded by K. Gilyard.

Motion Carried.  All votes were in the affirmative.  There were no abstentions.

 

Communication

R. Blazek had the following communication from the Board of Selectman (“BOS”):  They are concerned about the rising cost of the in project.  They are split in favor of renovating the Gymnasium.

 

G. Waugh reported that the BOE still had concerns about the traffic patterns; particularly the bus and parent drop off.  

 

J. Healy reported that the contract for the Geo Tech. work was sent to Michael Rybak for review.  Attorney Rybak had comment and the contract went back to T. Callahan.

 

Motion was made by M. Bramley toad an item 3A to the agenda for a discussion of the Gymnasium and take any appropriate action, seconded by K. Gilyard.

Motion Carried.  All votes were in the affirmative.  S. Kavle and J. Mullen abstained.

 

 

Presentation of Gymnasium Options – Herbert S. Newman& Partners

 

We are all concerned about the construction budget and a number of related  issues:

1.     The scope and budget of project are same with no allowance for the unknown and issues related to the construction environment including the considerable increase on the cost of building materials, specifically steel.  The Construction Manager (“CM”) has raised concern whether or not this project C-5M can be done for $33M.  We have been looking at ways to save money.

2.     As we move forward, other needs have become apparent at LIS.  We have been looking for ways to save money.   We believe we can save a great deal of money if we renovated the existing Gymnasium rather than demolish it.

 

Richard Munday review plan C-5M including the new addition, the front entrance, the location of the administration offices, new gymnasium and other classrooms.  This plan calls for the demolition of the existing Gymnasium and building a new Gym in a different place.  He questions whether it would make sense to save the Gym, if it can be renovated and it deficiencies addressed.

 

Richard Munday then reviewed concept D-5 including a new administration (same as C-5M), existing gyms stays with renovations, a new wing of 7-8 classrooms.  At the center of the school will be the common areas shared by grades 7-12 but classroom areas will be separated 7-9 & 9-12.  The new concept was given to CM for pricing to see if a cost savings will emerge.

 

He believes Concept D-5 will better serve the school.  It creates separate academies and centralizes the shared functions.  Another alternative to this plan is building a new Gym on the current footprint.   If it came down to the fact that this was not possible due to the budget, we can default to a renovated Gym.  This plan offers protection from the uncertainty of the construction climate.

 

Bruce Walpole of O & G Industries estimated at the last meeting that concept D-5 would be approximately $800,000.00 less than C-5M.   He also stated that with the site work that has to be done, Plan C-5M will be over $33M.  Whatever the outcome D-5 would protect the project scope.

 

Kent Gilyard stated that if the BC goes with the plan to renovate the Gym it had to be in the plan and budget that the run off and locker rooms be addressed.   Richard Munday – O & G allowed for addressing al issues connected to existing locker rooms. An Aerobic room and weight room will be added as well.  It will be renovated to address functional deficiencies.

 

Mac Bramley – From my perspective we are way ahead for ourselves.  If we are above budget I asked if there were any program alternatives.  The answer was “No”. This design gives us the flexibility to stay within the budget and stay within the Ed. Specs.  I commend the Architect for coming up with an alternative plan.

 

Gary Waugh reminded the BC that the critical issues involving the Gym was Lobby Space, Enhanced Bathroom Facilities, Locker Rooms, Bleachers on both sides of the Court, the Run Off and the Leaky Roof.   These issues would have to be addressed before I could get behind a renovation.

 

Robert Blazek also said that it has been decades that people have complained about the Gym.   He asked if there will be a need for an administrative staff in the 7-8 grade wing.  Richard Munday pointed out that travel of the 7-8 graders from the office and common areas is equidistant to the 9-12 graders.   Tim Breslin, Principal at LHS thinks that concept D-5 is a better plan.  He does not foresee, for the 7-8 grade wing, having to hire additional administrators.

 

Bruce Walpole – In October 2003 we had a plan with no new Gym for $32M.  In January 2004 we had a project that came to $33M with no site work.  We have no money for run off and no money to move bleachers.  The scope we can afford is D-5 as a renovation.

Jeff Zullo – I don’t think the site work is sacrosanct.  I am concerned about presenting concept D-5 with no change in the Gym.  Richard Munday – We are learning about the importance of the run off and bleachers in a renovation scope of the Gym.  We can include these things, but will have to find the money somewhere else.   Jeff Zullo – The current concept of building the new Gym stands with this Community.  Can we continue with renovation of the Gym as an alternate to building a new Gym on the footprint of the existing Gym.?

 

Richard Munday – We have finished schematic design of C-5M.  We can give it to O & G and get the cost estimate.  We will know in a few weeks what the cost is.  Jack Healy – The schematic design is part of your basic services.  If we decide to go with D-5 in the next few weeks, will that work be part of basic services.

 

[After much discussion the Architect concluded that if D-5 was chosen tonight (with a plan for a new Gym) that work will be part of basic services.  In the meantime O & G will do a cost estimate of plan C-5M and concept D-5 as part of their basic services.   If then the BC were to go back to C-5M after choosing D-5,  there will be additional cost.]

 

Stacey Kavle asked if BC felt C-%M was a superior plan that D-5.   Richard Munday stated that they believed D-5 is a better concept because it gives alternatives, the mechanical systems will remain in plan and they can deliver more for the budget with concept D-5.  

 

Bruce Walpole explained that the renovation would be more than Targeted renovation but not gutting of the building.  

 

Robert Blazek asked about the reimbursement rate and was told it would be higher for a new Gym, but we will not know what the reimbursement rate is until the end of the project. The fact is the BC must stay within the $33M gross. 

 

Stacey Kavle – We are presented with two plans, one of which, down the road, will give us some cost saving alternatives, the other will not. The concerns about the Gym that I heard were about the Lobby and the appearance.  It would be irresponsible of us to go forward without examining plan D-5.  

 

Greg Oneglia – In October there was so much new square footage (“SF”), program renovation SF and targeted renovation SF.  Against that SF we applied unit prices.  We came up with a $32M project.  The BOS decided to go with a $33M referendum.  As the plan progressed a plan to demolish and rebuild the Gym became a part of the plan.  We then came up with a plan for $33M with no contingency going into the referendum.  We had escalation in numbers but nothing for site work.  Now there is dramatic site work at both schools.  If there is a budget crunch the only place money could come out is targeted renovation.  That is when concept D-5 was developed.   With the schematic design phase complete we can develop a very accurate estimate.  We believe C-5M will be over $33M and D-5 gives us room.  The tremendous steel and material escalation has shocked the construction industry.

 

Mac Bramley explained that the current plan does have 2.5% per year construction contingency and 5% change order contingency.   The contingency O & G was talking about was the $1M cushion we had in October.

 

Public Participation

Bill Deacon – We need a new Gymnasium.  We have to establish a plan, get an estimate and make a decision about what is in and what is out.

Bibi Veerman – It seems to be poor design on the part of the Architect firm.  If the mechanical systems under the Gym are so important, why was this not thought out and included in the C-5 plan?

 

John Mullen – We hired Newman, we knew the cap was $33M, now we have a new design to save money, but is it going to cost us more in design money to get there?  I understand that C-5 is going to be over $33M which we can not do.  D-5 is a better option to keep the cost under budget.

 

Richard Munday – We have an obligation to explore options and make recommendations.  We have done that.  My concern is being reasonable in the amount of time we spend on a design concept when we have another concept being considered. 

 

Mac Bramley asked how long it would take to price C-5 and was told by the CM they were planning on having it at the next meeting on August 5, 2004.   Jeff Zullo – We don’t have a firm estimate on C-5.  To make a decision to change course tonight is irresponsible.   Tim Callahan – All  numbers are within striking distance on both plans.  There is more of a comfort zone and contingency with D-5.

 

Kent Gilyard – A couple of us on the Design Committee have been going to New Haven with Tim Breslin, Greg Oneglia and Bruce Walpole.  D-5 evolved out of discussion and problems that came up.  We have a plan that administrators like, it is easy to work with and gives us room in the budget.  Furthermore it functions better.  Site work costs are astronomical, the pipe lines, the paving.  Do the best with the Gym and if we have to decide to renovate, we will.

 

Lynn Chapman – It would be a shame to bring C-5 this far and not have it priced out.  If we need to schedule a special meeting to keep us on track, we should do that.  Mac Bramley – O & G is pricing C-5 anyway.  I was going to make a motion to recommend a parallel pricing.   We can go to D-5A with new Gym and cut alternatives or if we are still over we can renovate the Gym.

 

Motion was made by M. Bramley to go ahead with D-5 with a new Gym for Schematic Design, seconded by K. Gilyard.

 

Discussion

Bruce Walpole – The Schedule is based on a plan that Schematic Design will be done and Detailed Design will begin today.  If the BC accepts this Motion we will still be on schedule.  If we then go back to C-5 we will be off schedule.  The C-5 estimate will show the BC and Community that we can not support C-5.  Jack Healy – We have taken many votes to get to C-5 and modify the plan, it is a continual process.   Jeff Zullo – I think D-5 is much more complicated and a major mistake for the BC to take.

 

Motion Carried. Vote on the Motion:

J. Zullo – No

R. Blazek – No

L. Chapman – No

G. Waugh – No

K. Gilyard – Yes

J. Mullen – Yes

S. Kavle – Yes

M. Bramley – Yes

J. Healy – Yes (breaking the tie)

Traffic Consultant Presentation

 

Sharat Kalluri, Traffic Engineer of Wilbur Smith Associates and Raymond Gradwell, Civil Engineer of Diversified Technology Consultants Reviewed sketches of several alternative plans for LHS and LIS Parking and Drop off, made recommendations and answered questions relating to sizes, numbers of spaces, patterns and congestion of drop off and pick up.  They are also working on trying to have minimal site work.

 

BOE Member Frank Simone thinks the BC can save a lot of money leaving parking the drop off as is.   Tim Breslin disagreed. 

 

Concepts of the Exterior of LHS and LIS

 

Richard Munday spoke briefly about concepts of the exterior of LHS and LIS.  The current buildings include load bearing walls, pained concrete blocks, roof overhangs.   He would like to use these features in the new construction.  Some suggestions for new construction were as follows:

            LHS

            Enlarge windows on cafeteria; use load bearing construction in most areas but at administration office  build out of stud construction and use horizontal painted metal siding; raise ceiling at entrance and have a canopy.   He also reviewed drawings of new Gym and potential roof alternatives.

            LIS

            Punch openings in existing Gym walls and put in small windows; stage expansion should be metal and painted a bright color; the Link to cafeteria should also be a bright color also of corrugated metal with glass; New Library/ Administration Wing should be painted a different bright color and a lot of glass at the entrance.  At the bottom level want to cut in and drop of the sills to bring in more light.

 

Finance Update

After tomorrow there will be no more opportunity to get travel reimbursement.

 

Playing Fields

Jeff Zullo – The fencing around the fields is estimated at $75,000.00 to be installed by summer 2005.  The BC has committed to fencing and bathrooms, phone lines and data cable.

 

Motion to adjourn was made by M. Bramley at 10:15 PM and seconded by K. Gilyard.

Motion Carried.  All votes were in the affirmative.  There were no abstentions.

 

Respectfully Submitted,

 

 

 

Kelli L. Green, Recorder