MINUTES
LITCHFIELD
SCHOOL BUILDING COMMITTEE
LITCHFIELD INTERMEDIATE SCHOOL LIBRARY
SEPTEMBER 2,
2004
A meeting of the
Litchfield School Building Committee was held on Thursday, September 2, 2004, at 7:00 p.m. in the Litchfield
Intermediate School Music Room.
Present were: Jack
Healy, Chairman; Mac Bramley; Bill Buckley; John Mullen Jeff Zullo, Gary Waugh,
Kent Gilyard, Stacie Kavle and Lynn Chapmen.
Also Present: Peg
Perusse; John Tindall-Gibson; Tim Breslin; Anne Stillman; BOE Members, Frank
Simone, Wayne Shuhi, Don Falcetti and Diane Knox; Leo Paul; Richard Munday and
Steve Collins of Herbert S. Newman Partners; Greg Oneglia and Bruce Geban of O
& G Industries; Public and the
Press.
Meeting was called to
order at 7:00 PM Jack Healy
Approval of Minutes
Motion was made by Stacie Kavle to approve the minutes of
the August 19, 2004 meeting, seconded by B. Buckley.
Motion Carried. All
votes were in the affirmative. There
were no abstentions.
Public Participation
None
Communication
Jack Healy received two communications from Architect which
he emailed to all members of the Building Committee (BC).
Jack Healy received an email from Alan Landau requesting a
second public participation at the end of the meeting.
Motion was made by Mac Bramley to
add item 10A, a supplemental Public Participation to tonights agenda, seconded
by Gary Waugh.
Discussion
If people want to stay, we should
answer their questions. If someone comes
in late and misses part of the presentation, we shouldnt allow them to ask questions.
Motion Carried. All votes were in the affirmative except Bill
Buckley and Jeff Zullo who voted in the negative. There were no abstentions.
Architect and Construction Manager Present Estimates for C-5
Design Greg Oneglia
All members were given the C-5 estimate for Litchfield High
School (LHS) and the estimate on Litchfield Intermediate School (LIS). The cost is over the $33M budget by
$3.8M. The BC did their job, as the
Architect and BC proposed things the Construction Manager (CM) reacted. You now have just about everything wanted by
the Town in this plan. If we can afford
them, good; if not you can cut back. When
the project was conceived a second story addition was in the plan with nothing
to the front of the school. There was no
reason for the site work in the budget.
As the project evolved changes were made. One of the big drivers of the overage is:
site work of $1M; sprinkler system, which we were not planning for the entire
buildings, of $800K; and the tremendous increase of steel, oil and lumber, 5
10% in material price increases.
Greg Oneglia passed out possible changes to reduce the
price:
eliminating site and sprinklers in
all but the new construction;
using existing stairwell in new
addition LIS;
no expansion of the stage at LIS;
change the connector to the
cafeteria to a canopy connector.
With ideas like that, the savings was $1.5M over of the LIS
budget.
Until this estimate, O & G has never had a set of
drawings where we can quantify the materials being used. We estimate what we see on the drawings, but
we also carry an Estimate Contingency.
As the drawings evolve the Contingency will decrease and costs will
increase.
Richard Munday We know that we are over budget and
understand where. He distributed an
additional list of items where savings can take place. This list did not have savings estimates and
the BC asked that the Architect come back with the list formatted similar to O
& Gs list, with the proposed savings next to the suggested cut. The primary suggestion related to
Mechanical, Electrical and Plumbing systems and they suggested saving money by
examining the systems to find out if any can be saved and rehabilitated.
Workshop Session for C-5 design Estimate
Litchfield
Intermediate School
Gary Waugh - What is the average age of the facilities in the schools and what is the
life span if it is upgraded or rehabilitated.
Steven Collins The equipment at each school is a different age. At LIS the equipment is the age of the
building. At LHS the equipment related
to the different additions done on the building. I dont think we can guarantee a 20 year
life span for the equipment that remains.
Bill Buckley We need to have some idea of how long the rehabilitated equipment will
last. Is there a chance within one year
that we have to replace the boilers?
Richard Munday We are only recommending that this is a way to save money. We have not yet evaluated all the
equipment. This is what we are
proposing, to go down this path.
Bill Buckley You make these recommendations, we have to have a better answer about
life span than what you gave us.
Mac Bramley The 18 inch drain in the courtyard is not working as it should. I dont see that drains have been looked
at. The roof needs to be replaced. It is in critical condition. There is a warranty and we can negotiate so
we can reduce the cost to replace it.
Steven Collins We can minimize the cost of the roof via state requirements for minimum
roof pitches. When you take an existing
roof structure such as the one at LIS, a ½ pitch per foot is very costly. A drainage system is not required.
Richard Munday We need to look at other ways to save money and look for another
approach.
Mac Bramley Because I dont have the estimate for D-5 I feel uncomfortable talking
about LHS. This numbers here at LIS were
a surprise. Several of us spoke about
locating the administration wing in the front of the building, between just
behind the front entrance and the Auditorium, knocking out part of the corridor
and building partially into the courtyard.
The challenge is getting equipment in to do the work. There is a 12 foot clearance, which is tight
but adequate to get equipment in and out.
Jeff Zullo Macs point would save significant amount of construction and site
work.
Mac Bramley The existing stage is as deep as any theatre consultant would
recommend. Is it possible to put in a
modified lean-to and punch two doors in it?
Then you can walk in and out of the building.
Kent Gilyard I think not putting a roof on this building (LIS) would be a last
resort. We have had nothing but leaky
roofs for 25 years.
Bill Buckley The main criticisms that the first building committee received was not
doing anything with the roof. I would
like to see a built up roof. I have some
specs for such a roof.
Jeff Zullo The LIS expansion as planned at about 7600 SF and now it is 8512
SF. Why?
Richard Munday Probably because we go from inside wall to outside wall and the estimator
goes from outside wall to outside wall.
Stacie Kavle Looking at what we have and what we are trying to ascertain, what can
be reused and what need to be replaced?
How quickly would you be able to get back to us so we can make a
decision?
Steve Collins I would like to think it can be done within a few weeks; within three (3) weeks time we can provide a
good amount of information to make decisions.
Gary Waugh How pragmatic is an open air connector [to the cafeteria] and how would
it function in the middle of the winter?
Will there be indoor access?
Richard Munday Students at private schools go outside during the winter to travel to
classes. In public schools, during the
winter, we try to keep students inside.
For a health standpoint there is no data about kids who go to private
school versus kids who go to public schools.
We are also suggesting keeping the stairwell from the gym.
Gary Waugh The students would have to then walk through the Gym, a learning space,
which is not an optimum scenario.
Jack Healy Did you think about security?
Richard Munday It would be necessary for the staff to supervise.
Mac Bramley The students will need coats in the middle of winter. Functionally, an open air connector wont
work. I have always heard concerns
about the windows, plumbing and air quality. This project, it has to look new,
clean and fresh when completed.
Richard Munday We are not suggesting that this will look less new than otherwise. We are looking at savings money on the scope
of the project. If we can be very
forensic in studying the M/P/E systems, we can save money. We may want to do research past renovation on
equipment and how they lasted and whether the schools were happy.
Bill Buckley I would like to hear a better explanation of what we are looking
at. Are these choices or are they
suggestions.
Greg Oneglia After generating the budget, we kicked around ideas to realize
savings. If you go with C-5, you have a
$3.5M problem. What we have to do
together is come up with a list to reduce the cost.
Bill Buckley This is normal activity. We are
either going to be over or under budget.
The other point that Mac made was very important. This BC went through a public exercise to
hear what they have to say. It is
important that we listen to their concerns.
M/P/E need to be addressed and at the top of the list. What if we didnt expand anything, just
renovate? I would like to see
evaluation done, eliminating the office and library at LIS and same at LHS; the
guidance office. We are building it at
the expense of the students.
Richard Munday The program requires space for classrooms.
Bill Buckley If we need classrooms, build and renovate classrooms.
Mac Bramley Can we get from O & G a list of things we talked about with savings
amounts?
Jeff Zullo In these estimates we are carrying an additional contingency.
Greg Oneglia When we get to his level of drawings we add this estimate
contingency. New addition is $156 per
SF, it was prices at $165 per SF historically.
As these drawings evolve, the design
estimate contingency will disappear and the dollars will go into that SF cost.
Bill Buckley We should consider not building the office and media center; that would
save a lot of money.
Gary Waugh We are governed by the fact that we need to meet the Ed Specs.
Bill Buckley Maybe you have to modify the Ed Specs to get the job done.
Greg Oneglia - We are pricing eliminating site work and sprinklers to save money.
Jack Healy We have to put sprinklers in the new addition.
Steve Collins If no significant modification is made in the Auditorium we would only
need sprinklers in the new addition. The
money for the fields was not considered in this estimate.
Greg Oneglia I thought you were supplying a hose to the fields, I didnt think we
were supplying an irrigation system.
Jeff Zullo The Playing Fields have decided to tap into the town water; the
irrigation demand is more recent.
Greg Oneglia In the budget we are now carrying $94K for fences for the playing
fields. Now, if you are talking about an
irrigation system, this is driving the budget up.
Bill Buckley If we dont have to do sprinkler work we dont need to upgrade water
line. Site work is eliminated.
Jack Healy Have you left money in the budget to resurface the parking lots?
Greg Oneglia No, we will protect the parking lots.
Jack Healy I hope for the next meeting we can have the two lists of proposed
savings put together in O & Gs format.
Bill Buckley We have to do something for the theater. I like the lean-to idea. I dont think we want to vote for these ideas
now. Lets get a cost evaluation and
then we can choose.
Jack Healy I think there has to be research done, something like the tank, we may
have to remove it after so many years.
We also should talk to the Fire Marshall about the sprinkler system.
Richard Munday The Fire Marshall has a lot of discretionary authority. Even if we dont need sprinklers, he may
require something just as costly to offset it.
Mac Bramley If the Town wanted to find an alternative way to fund fences at the
Playing Fields, we can use this money somewhere else. The main water line can be donated to
Aquarian and they could take care of it.
Bill Buckley We should look at a hydraulic analysis.
Is the capacity limited because of size or because of crud inside the
pipes. If we clean it out, will that
improve the flow enough?
Steve Collins We have done a flow test. The
problem is residual pressure.
Mac Bramley That is Aquarians problem. It
is the main pressure that falls off when you open it.
Gary Waugh I hope when you bring information back to us, I hope you will have
talked to the staff in that department before the expansion is eliminated.
Jack Healy If we reduce the scope of the project, can we reduce some of the
consultants?
Bill Buckley We should carry an allowance for paving the parking lots. I think the Town made it clear that they wanted
storage for the theater and a way to move from stage left to stage right. Also, I would like to see the curtain
separated from the rigging. I also like
Macs idea of putting administration up front.
Stacie Kavle The cafeteria does not have a full working kitchen. The plan shows a full working kitchen. That may be something we can modify.
Peg Perusse Presently it is operating in a very small space as a full working
kitchen.
Jack Healy I wont compromise on roofs. We
heard air quality is a concern and we have to improve it.
Jeff Zullo Are you planning to take out the carpeting and replace it with vinyl
title?
Gary Waugh In the areas where there as been water damage, it have been replaced or
cleaned. It is premium quality carpet
and can be lifted up and put back down anywhere.
Wayne Shuhi What do
we have projected for portable classrooms?
Greg Oneglia - $500K.
Wayne Shuhi It is not beyond the realm of possibility to move a grade to the Center
School during construction.
Litchfield High School
Jeff Zullo When we made a decision to forward D-5 to cost it out, it was clear
then that D-5 was less costly then C-5.
We are going to have a lower cost estimate. Working on LHS now is redundant.
Bill Buckley We have to give O & G an opportunity to give us the price of
D-5. I would like to see if we can
massage C-5. If we have savings at LHS
we can apply it here to LIS. I would
like to go through the exercise of looking at cost savings at LHS now.
Richard Munday It was our intent in July to go with the D-5 plan, with the new
gymnasium or a default renovated gym.
Jeff Zullo C-5 with four cost savings ideas
- this cost is with a new gymnasium and new mechanicals
Richard Munday D-5 was more efficient because of the location of the boiler room. The value of D-5 is that is has the default
to a renovated gym. The school
administration thought it was a better plan.
Estimating C-5 was not for the purpose of pursuing the concept, but to
have an estimating exercise.
Stacey Kavle I voted to switch to D-5 because of the default.
Jack Healy I voted to switch to D-5 because there was an anticipated savings
because of the mechanicals. I think we
are within a whisker of coming within budget on C-5; D-5 should be a greater
savings.
Greg Oneglia D-5 creates a separate campus for the 7-8graders, puts the gym where
the existing gym is, which creates a default, intellectually we thought there would
be savings because of mechanicals.
Bill Buckley We are in the development stage where we are engineering this . We need to look at costs. To say we have to stay with the D-5 plan,
that is ridiculous. We are not going to
sit here and go down a road which might be more expensive. We want to see an analysis like we did
tonight.
Lynn Chapmen I am curious how binding the agreement was to go with D-5. You put us in a corner.
Jeff Zullo My criticism of the Architect, forcing that decision, we do not have
estimated to make that decision.
Richard Munday I think we are having this conversation prematurely.
The BC reviewed O & Gs proposed cost savings ideas at
LHS.
Bill Buckley I would like to see an allowance for site work at LHS. Eliminating sprinkler is okay as long as it
is approved by the Fire Marshall. We
need the cost of Newmans narrative and a detailed evaluation of the
mechanicals we want to reuse.
Jeff Zullo We have furniture, equipment, telephone systems and $542K for
technology. We are driving program and
SF reductions and we have these numbers for technology. We are not sure where they came from. I dont want to carry numbers that have no
meaning.
John Tindall-Gibson We can cost out number for furniture, equipment , telephone and
technology.
Jeff Zullo We have a bonding plan. I will
try to come back in two weeks with that plan.
Invoice Approval Discussion
Mac Bramley I met with the new Fiscal Control Office and
Stacey Dionne today. I should be able to
bring back something for consideration at the next meeting.
Schedule
Richard Munday I can not comment on it at this point. Bill Buckley Are you proceeding with D-5?
Richard Munday Yes. Bill Buckley We
need the numbers. Jack Healy In July
we gave the Architect the go ahead with D-5 with the default and savings
because of the mechanicals. Mac Bramley
D-5 was the preferred plan of the administration.
Motion was made by Bill Buckley to put D-5 on hold until the
BC can do a cost comparison with C-5 and make a decision, seconded by Zullo
Motion Carried. All votes were in the affirmative. There were no abstentions.
Playing Fields
Jeff Zullo The track and lower area will be excavated this
fall and the upper fields will be started in the winter. The plan is to have track and lower fields
ready for fall of 2005. I will discuss
with Tim Callahan and Ed Fabbri about the irrigation system.
Public Participation
Alan Landau I have been reading the minutes. It seems there is a lot of arrogance and
uncertainty about what is going on. It
seems that Newman is not doing what is requested of them. I am concerned about maintaining existing
mechanicals. If that is the way to go. I am concerned about what the reimbursement
will be.
Wayne Shuhi Thanks, I appreciate everyones hard work.
Motion to adjourn was made by Mac Bramley at 9:55 PM,
seconded by Lynn Chapmen.
Motion Carried. All votes were in the affirmative. There were no abstentions.
Respectfully submitted,
Kelli L. Green
Recorder