Corrected MINUTES
LITCHFIELD
SCHOOL BUILDING COMMITTEE
LITCHFIELD HIGH SCHOOL CAFETERIA
SPECIAL
MEETING
OCTOBER
27, 2003
A special meeting of the
Litchfield School Building Committee was held on Monday, October 27, 2003, at
7:00 p.m. in the Litchfield High School Cafeteria.
Present were: S. Kavle, K,
Gilyard, B. Buckley, J. Zullo, M. Bramley, L. Chapman, P. Sapiro, voting as
full member, J. Mullen, alternate member
Also Present: Tim Callahan,
Architect of Herbert S. Newman & Partners, J. Tindall-Gibson,
Superintendent, P. Perusse, Business Manager, Diane Knox, BOE Chairman, BOS
Members: Harold Fairchild; Don Falcetti and John Noone, J. Zinn, First
Selectman, State Senator Andrew Roraback, Representative Craig Miner, Tim
Breslin, Principal LHS, Public and the Press.
Meeting
was called to order at 7:00 PM by Chairman S. Kavle
Members of
the School Building Committee Introduced themselves to the public.
Presentation
S. Kavle
gave a brief introduction about the submission of the ED 049R with the cap of
$33,000,000 and reviewed what the Committee has been working on he passed two
months.
Tim
Callahan made a presentation to the public which included the following:
Committee’s work is still early on in the process; Committee
has defined parameters; Committee is
currently only responsible for getting the ED 049R to the State; Submission of ED 049R so flexible enough to
have room to work with project to be able to manipulate size, scope and use;
Need public input on what components are important; Looking at affordable REUSE
of existing facilities; Submission Deadline is October 31, 2003 and State
approval around December 2003 with Referendum in February 2004.
Review of
the Committees Priority Summary:
Construct, Alter and Renovate Building Area to Meet Education Needs
Stabilize the Existing Buildings (Safe/Functional/Sound)
Optimize Reimbursement
Limit Site Development to Safety and Security Issues
and BOE Priority List
1. Stabilize Infrastructure
2. Technology Infrastructure & instructional opportunities
3. Expanded & modernized science labs
4. Expanded fine arts & performing arts capacity
5. Improved athletic fields
6. Improved traffic & safety
7. Communication & security
8. Interior finishes and classroom learning environment
upgrades
9. Staff work areas
10. A plan to manage the minimizing of the disruption to the
learning process throughout the renovation process
and
Flexibility
with New Construction (i.e. the LIS and LHS Auditorium)
with Existing Alterations
(renovate as new or Target renovations)
with State Reimbursement
Channel Alterations down the right path
New Construction
Program Renovations
Energy Conservation
Code Updates
Mechanical Upgrades
Hazardous Material Abatement
Rebates
Private Funding
At
Litchfield Intermediate School two issues are: New Cafeteria and New Media
Center & Library
Committee
has selected Target Renovation for both schools. At LIS 5,000 SF of program renovations. At LHS 12,000 SF of program renovations.
Also working
on how to reuse buildings more effectively with the greatest reimbursement:
Some
projects that can be 100% Reimbursable
New Constructions
Program Alternatives
Energy Conservation
Code Updates
Mechanical Upgrades
Hazardous Material Abatement
Issues for
State Filing:
Define amounts per school
Grade enrollment per school
Address and Define Scope of Targeted Renovations & new construction
How to
reuse LIS & LHS - see Architect’s: 074-0035 Litchfield Intermediate School
Plans:
Expansion
of Existing Auditorium
Reuse of Existing Auditorium
Demolition of Existing Auditorium
Also see
074-0034 Litchfield Middle/High School Plan
The “old”
ED 049 was displayed and explained that the new and revised ED 049R will be
submitted with new figures with a total of not more than $33,000,000
b. Buckley
asked T. Callahan to explain ho w the State determines reimbursability -
Current reimbursable rate is 41.43% so when it say 100% reimbursable it mean
41.43% of the figures will be reimbursed.
Formula also describes maximum allow space in SF that State will
reimburse for . LIS will be above this
allowable space (after the addition)
G. Waugh
arrived at 7:15 PM
M. Bramley
discussed the belief by the Committee that this project is debt service driven
and asked the public how many would agree at a 5% increase, 10% increase or 15%
increase. Is there a number the Town
will accept as to what the Town will pay annually for this project; the stay
within the $33,000,000 cap Town would be responsible for borrowing $24,000,0000;
Mill Rate from 2007 to 2017 could increase up to 4.19 mills and drop below 3
mill increase after 2017; discuss using untraditional methods to reduce this
increase to 2 3/4 mills instead of 4 mills including adding more time to pay
off debt and private funding
Public Participation
Kim Beres
questioned whey the last project of $37 M was to have generated a 3.16 M
increase and why it would be more now with the lower interest rates. - This has
to do with the amount that is reimbursable by state and debt service. When you Renovate as New, as was proposed in the last project, more of the project is eligible for
reimbursement - Committee is still studying this to maximize reimbursements.
Bill
Dranginis asked if changing the Auditorium to a Library and Cafeteria and
building a new Auditorium at LHS would mean more reimbursement. - It would be more reimbursement but it
doesn’t out weigh the cost of the project and is higher than Target Renovation.
Kevin
Creed commented that stretching the Bond out for a longer period of time can
help people on fixed income and when newcomers move to Town they will have to
pay their fair share.
Bill
Dranginis asked why not go with a project of higher gross cost and lower net
cost to Town?
M. Bramley
stated Committee would present a $33M project but asked if taxpayer should be
allowed an alternate project to study:
i.e. $37.5 M. Project - Town cost $23M
$33 M. Project - Town cost
$24M
Diane Knox
state that it doesn’t make sense to bring anything more than the $33 M to the
taxpayers.
K. Gilyard
questioned if taxpayers understand that you can build more school and pay less
taxes with a higher cost Renovate As New Project. Public comments included “keep it simple” and
“can we change the project after the ED 049R is submitted.”
T.
Callahan explained that changes can be made within 10%of the figures
submitted. It has been filled out to be
flexible and at this time Committee may not see what alternative may be and may
find something else that is reimbursable later.
B. Buckley
clarified that the Committee had picked 11.1M of LIS and 21.9M for LHS so there
would be flexibility to increase one and therefore decrease the other and within that 10% margin the LIS
figure or 11.1 could be increased to the cost of the “Renovate As New” plan.
Committee
would like to have more forums like tonight’s to inform taxpayers of what they
are doing and get input form public regarding what you would like to see in
that project. Regular Meetings are the
first and third Thursday of the month.
J.
Endicott suggested that Committee inform public what they will be voting for in
February 2004 by sending out brochures as was done last year and questions
whether there was enough money in the budget to do this.
J. Zullo
explained that Committee has a $50,000 budget and $12,000 was allocated for
such a brochure which would first have to be submitted to the State for
approval so that it is unbiased. He also
stated that public has to be aware the Committee had a $33M cap for project
proposal and that the BOS, BOF and Town Treasurer are responsible for Bonding
and Mill Rate.
Kim Beres
questioned whether the State will allow only 20 year Bonding and J. Zullo
explained that State will reimburse if building has 20 year life – 20 year
Bonding is not a policy, just a practice.
J. Healy
arrive at 8:00PM
Ed Fabbri
questioned if Committee is planning fancy entryways and administration offices
instead of classroom. Committee stated
that they are trying to optimize dollars for kids and Science and Technology is
a high priority and commented that Tim Callahan had done a good job trying to
deliver a project that Town would feel comfortable with.
Kim Beres
questioned whether Herbert S, Newman and Partners who are filing the ED 049R
are necessarily going to be the Architect for this project. Committee stated that they will be
interviewing both Architects and Construction Managers including Herbert S.
Newman and Partners and O & G.
J. Healy
reaffirmed that this is just the filing phase right now and the next phase will
be the layout of the school programs, classrooms, etc.
M. Bramley
stated that for this phase there was a need to hire and Architect and
Construction Manager to help with the Ed Specs and assist in how to divide the
$33M between both schools.
T.
Callahan mentioned that he funding proposed will not include athletic fields,
bus loops & drop off.
Doyle
Finan commented that the LHS Gymnasium sits off by itself right now and during
breaks there is only a small space of people to go to with deplorable rest
rooms and asked that the Committee make as part of the project a plan for
expansion of this room and upgrade of the rest rooms.
Public
also commented about the LIS Auditorium where there are currently buckets for
leaks on the stage where the students are practicing for the school musical and
remembers that buckets were one the stage in 1969 when he was in school.
The public
also asked how the upgrade of athletic fields be paid for. And Committee repeated that the fields are
not part of the project and external renovations could not be done with the
$33,000,000 cap. M. Bramley felt that
Committee should encourage community to do everything they can to raise money
and also try to get private funding and it’s not uncommon to find corporate
funding.
The public
also commented that is important to also have an aesthetically pleasing
building.
Submission of ED 049R
Drafts
were passed around to the Committee with the following numbers:
LIS $11.1M
LHS $21.9M
Administration Office $0.00
Motion was
made by B. Buckley, sec. by M. Bramley that Committee approve the ED 049R for
$11.1M for Litchfield Intermediate School, $21.9M for Litchfield High School
and $0.00 for Administration Office and forward to Board of Education for
review and approval.
Motion
Carried. All votes were in the affirmative.
There were no abstentions.
Review and take on RFQ Submissions
for the Architect and the Construction Manager.
J. Healy
suggested Committee establish a schedule for review RFQs and each member should come up with a
short list to the next meeting.
Committee
discussed that in order to schedule
this Committee should look at an end
date and work back from that . For last
committee it was a four week process; reviewed; pared down to five f for
interviews then two for final interviews.
Committee should establish date they want the firms on contract. Referendum in February 2004 so need to have
the selection complete by December 1, 2003.
Two months to develop conceptuals is a tight time frame. Next Regular
meeting is November 6, 2003.
Motion was
made by J. Zullo to schedule a special meeting on October 30, 2003 and November
13, 2003 for the purpose of selecting the Architect and Construction Manager
for the project. Sec. by B. Buckley
Motion
Carried. All votes were in the
affirmative. There were no abstentions.
Committee
discussed that member can pick up to five to bring to Thursday’s meeting –
looking for common ground and may find only three firms to interview. Asked P. Perusse to provide Easels for next
meeting. Prioritize the five selections
and the Goal will be to come out of the meeting with a short list to interview.
J. Zullo
stated that previous committees have selected just one Architect and one Construction
Manager – would this Committee contemplate going forward with two of each to
bring a more competitive opportunity to negotiate the project. Committee is not limited in its selection
and can select the most qualified and ask that to down size their proposal.
B. Buckley
agreed toe select two qualified firms and ask to two proposals and make a
selection. We’ll see a net cost benefit.
Task for
Thursday night for each Committee to bring Five (5) Architect choices to
meeting.
Intent is
to hire someone that if Town votes to continue with the project at the February
2004 referendum, we stay with the Architect and Construction Manager.
Motion to
Adjourn made by B. Buckley and sec. by M. Bramley at 8:45PM
Motion
Carried. All votes were in the
affirmative. There were no abstentions.
Respectfully
Submitted,
Kelli L.
Green
Recording Secretary