Litchfield Schools Building Committee

Meeting Minutes

 

 

 

LOCATION                                                                   Litchfield Intermediate School Cafeteria   

 

           

DATE OF MEETING                                                     November 15, 2007       

 

 

TIME MEETING STARTED                                           7:06 PM

 

 

PERSON PREPARING THE MINUTES                          Marianne Arancio Stilson

 

 

MEMBERS PRESENT

 

1.  Jack Healy, Chair & BOS Representative

2.  Bob Blazek

3.  William J. Buckley, Jr.          

4.  Lynn Chapman

5.  Kent Gilyard                       

 

            

MEMBERS ABSENT

 

1.  Stacie Kavle, Vice Chair      

2.  Jeff Zullo, Treasurer & BOF Representative

3.  Mac Bramley 

4.  Gary Waugh - BOE Representative 

5.  Leo Paul - Ex-Officio

 

 

OTHERS PRESENT

George Graikoski of O&G, A. Brooks Fischer of Herbert S. Newman, Tony Crowe, Peg Perusse, and Wayne Shuhi

 

 

QUORUM PRESENT                                                     Yes    

 

 

1.  CALL TO ORDER

 

Jack Healy, Chair called the meeting to order at 7:06 PM.

 

 

 

2.  APPROVAL OF MINUTES

The approval of the meeting minutes of November 1, 2007 is tabled to next meeting for lack of quorum of the members present.

 

 

3.  PUBLIC PARTICIPATION

None.

 

 

4.  COMMUNICATION

 

Report from Jeff Zullo on BOF Communication

None discussed.  Jeff Zullo not present.

 

Report from Gary Waugh on BOE Communication

None discussed.  Gary Waugh not present.

 

Report from Jack Healy on BOS Communication

None discussed.  BOS did not have a meeting because of Election Day.

 

Correspondence

Jack Healy, Chair reports that the only correspondence was from Betsey Glassman and that correspondence was emailed to the members of the Committee.  He states that he has no comment on that correspondence.

 

 

5.  ARCHITECT/CONSTRUCTION MANAGER UPDATES

 

Budget (O&G)

George Graikoski of O&G hands out to the members of the Committee the following reports:  Litchfield High School/Middle School & Litchfield Intermediate School Monthly Progress Report No. 13, October 2007; Summary Data Report #13, October, 2007 for the Middle/High School and Intermediate School; Construction Manager’s Monthly Cost Control Report for the Middle/High School and the Intermediate School; Change Order by Trade Contractor for the Middle/High School and the Intermediate School; Payment Applications Summary for the Month of October for the Middle/High School and the Intermediate School; Project Commentary October 2007 for the High/Middle School; Phasing Plan for the Litchfield High School; Litchfield Intermediate School Project Commentary and Phasing Plan Second Floor and Third Floor for the Intermediate School.

 

George Graikoski goes over the reports for the Middle/High School with the members of the Committee and goes over the changes to the report from the last meeting.  

 

Jack Healy, Chair discusses the Middle/High Schools Owner’s Contingency line item with George Graikoski.   George Graikoski will adjust the Owner’s Contingency line item from the projected costs column to the funds available column for the next report.  George Graikoski will update the Technology line item with Deb and Peg because it hasn’t been done in two months.  Jack Healy, Chair will report to the BOS next Tuesday night at the meeting and make it clear to them that the project is not in the red as has been reported by members of the community.  George Graikoski will make the changes discussed this evening and email them to Jack Healy, Chair and the members of the Committee before Tuesday so Jack Healy, Chair will have the updated report.

 

William J. Buckley, Jr. feels that the Owner’s Contingency line item for the Intermediate School of $37,775.00 should be moved to a new line item entitled General Trades (2) line item for next report.  George Graikoski will make that change as well for Tuesday.

 

 

Motion:  William J. Buckley, Jr., moved that the Committee take from Owner’s Contingency which has a balance of $275,684.00 and move $37,775.00 out of Owner’s Contingency and into a new line item entitled 20-069101 General Trades (mill work).

So moved.  Seconded:  Bob Blazek

Discussion:  none.

Vote:

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None

All ayes

Motion passed.

William J. Buckley, Jr., feels that George Graikoski should make that change also before he emails the report to the Jack Healy, Chair for Tuesday night’s meeting.

 

Jack Healy, Chair reports that he heard from two contractors about outstanding bills.  Those contractors are Waterbury Masonry and Allied Restoration.   Jack Healy, Chair states that he spoke to George Graikoski and that the bill in question from Waterbury Masonry was just submitted on October 15th so the letter from the attorney that he received was not justified.  George Graikoski will speak to the owner about it next week.  George Graikoski states that they does not have any justification for the change orders submitted and that he will speak to them about this issue tomorrow morning.  He also states that he will respond in writing to the invoices  tomorrow morning and email it to the members of the Committee as well.  Allied Restoration claims that they have not been paid for any work since June.  William J. Buckley, Jr. feels that this is interesting since Ernie has made several comments about them not doing any work because they have not been paid and yet the Building Committee did not have any open invoices for them.   Jack Healy, Chair states that the Building Committee is not holding any invoices and that he spoke with O&G and they don’t have any invoices.  After investigation, it is discovered that Herbert S. Newman has the outstanding invoices that have not been submitted to the Building Committee for payment.  Peg Perusse states that A. Brooks Fischer handed her a package of invoices before the meeting this evening and that they are not prepared for the meeting tonight but that she will do whatever the Committee wants her to do with regard to the payment the invoices.  Jack Healy, Chair states that he spoke to Leo Paul, First Selectman and if the Committee wants to pay the invoices this evening, then he will get the checks cut next week.   A. Brooks Fischer does not know why the invoices where being held by Herbert S. Newman.  George Graikoski states that the invoices were for the metal siding and held because of the coping issues.  Discussion ensued as to whether the Committee should address these bills this evening.  William J. Buckley, Jr. states that the Architect should not be holding back bills from the Building Committee because the contractors are annoyed with the Committee and the Committee does not even have the bills to be considered for payment.  He states that bills should not be held back by anyone other than the Building Committee.  George Graikoski spoke with the owner of Allied and told him that the bills were going to be considered this evening and was very surprised that they called the First Selectman because he thought he had resolved this issue with them.  Bob Blazek wants to know if there are still issues with the invoices if they were to be paid tonight.  Jack Healy, Chair states that he will be speaking to Allied Restoration tomorrow and will let them know what the Committee decided. 

 

Jack Healy, Chair is concerned because he found out that the COR meetings on Tuesday mornings with O&G and Herbert S. Newman have not been taking place.  He is concerned that these letters and calls for payment will be the tip of the iceberg if these meetings do not resume. He instructs A. Brooks Fischer to tell Richard Munday that the COR meetings must be done once a week starting next week and continue every week from now on.  George Graikoski outlines the issues he is having because Herbert S. Newman is not showing up at the meetings and signing the paperwork that needs to be signed every week.  Jack Healy, Chair told George Graikoski that if he is having any trouble with these meetings, that he is to call him immediately.  He is concerned because this project is coming to an end and these items need to be resolved quickly.

 

Schedule Update (O&G)

George Graikoski states that at the Intermediate School they have the substantial compliance letter for the Media Center and the Gym vestibule and have not seen the TCOs.   Peg Perusse reports that there is an issue regarding the TCOs.  Jack Healy, Chair states that after John issues a TCO, he’s not getting the information to be able to issue a CO and this has been an ongoing problem. Jack Healy, Chair will take care of this issue tomorrow.  This issue is discussed in detail by the members of the Committee.  Jack Healy, Chair tells George Graikoski that if there are any issues that need to be addressed that are safety issues, they need to be done immediately and take priority.  Jack Healy, Chair discusses the issue of the topsoil and dressing and shows the members of the Committee a large rock that was run over by the lawn mover.  Discussion ensued about the issue of the top soil, where the rock was when it was run over and possible scenarios of how it got there.  Bob Blazek states that a student could have thrown it there and that it may not have anything to do with the site work.  George Graikoski will call Bob to find out where the rock was hit.   Jack Healy, Chair states that this work needs to be completed because he is getting complaints about it.  Jack Healy, Chair states that he asked Peg Perusse for the final plans for trees and landscaping so that these issues are done in accordance with the plans.  William J. Buckley, Jr. feels that the landscape architect should do a review of the entire site and do a punch list of the entire site of missing items, etc.  He feels that this would be helpful.  William J. Buckley, Jr. states that if it is something that the Building Committee is responsible for, then it should be in somebody’s bid to furnish these trees, etc.  Jack Healy, Chair feels that someone should make the effort to marry the drawings with the permits so they are in compliance because he is tired of these issues every month.

 

 

Intermediate School Media Center & Cafeteria Completion (O&G)

George Graikoski reports that he is waiting for COs. Jack Healy, Chair will forward the email from John to everyone tomorrow.   He also states that the desk tops are being worked on now and should be finished by Saturday.

 

 

Entrance to 7th & 8th Wing updates (O&G and HSN)

This work is done.   Jack Healy, Chair states that this agenda item should be removed for next meeting.

 

 

Wall Panel Update (O&G and HSN)

Jack Healy, Chair states that there still is an issue with the final mockup and that no one from Newman has come up to look at it.  A. Brooks Fischer states that Newman reviewed the mockup and sent a letter.  George Graikoski states that there is a problem because the contractor requested that Newman come out to the site and meet with them and O&G to review the comments that Newman made on the mockups because Allied stated that if they do what Newman wants them to do on the outer edge, that there will be problem with leaks.  George Graikoski states that to save time in weeks of emails, phone calls and letters and then have the he said/she said issue, it would have been easier to have the meeting that was requested by Allied to resolve this issue.   A. Brooks Fischer stated that Newman would be happy to come to the site if they knew what the issues were first.  He states that they issued a sketch a few days ago that should resolve the problem and hasn’t heard back from them.  George Graikoski states that it would have been easier and quicker for Newman to have just showed up for the meeting to discuss this in detail rather than through mail.  Bob Blazek agrees and wants to know why Newman did not show up to a requested meeting.  A. Brooks Fischer states that the only thing they got was a request for a meeting and that they asked why and when they found out what the issue was that they made a sketch and told them if it still is an issue they would come out.  Jack Healy, Chair states that this has been going on for weeks.   George Graikoski states that this has been a problem with Newman with the change order requests, the pay order applications and just about everything.  He does not feel that it is an unreasonable request to have the architect come out to the site to review a mockup that the contractor wants to look at.  He states that Newman has not been onsite since the beginning of October.  He states that they are losing weeks because they will not come out to the site when needed.  A. Brooks Fischer states that there is an issue with going onsite and doing things verbally and that they don’t want to do that.  Discussion ensued.  William J. Buckley, Jr. states that the contract requires that when requested by the owner, the architect will visit the site to resolve design issues and that this certainly is a design issue and that the Committee should require them to be on site to put this issue to bed.

 

Motion:   William J. Buckley, Jr. moved to authorize the Chairman to request the Architect to show up as frequently as necessary to resolve this issue and further moves to authorize the Chairman to make the same request of the Construction Manager.

So moved.  Seconded:  Bob Blazek

Discussion:  William J. Buckley, Jr. states that Richard Munday is aware of this provision in the contract and has it up on a board.

Vote:

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None

All ayes

Motion passed.

 

Jack Healy, Chair states that the will talk to Richard Munday tomorrow to get this resolved.

 

 

LHS Ceiling Replacement, Noise Attenuation and Noise Levels (HSN)

George Graikoski reports that the walls panels are up and although it is an improvement it does not work as well as the ceiling tile.  He states that he ordered more ceiling tiles to finish the wing.  Jack Healy, Chair states that he does not remember seeing a final price for this.  George Graikoski will get that for Jack Healy, Chair.

 

 

Credit Update (O&G)

George Graikoski is still working on the update and will have it for the next meeting.  He states that Anders finalized his list and met with the painter and GarSan and is still waiting to finalize those numbers.  He states that he is going down the list with the contractors and that this goes hand and hand with the change order request reviews that need to be done every week and if that starts up again he can get that finalized as well.

 

 

Issues List Review (HSN)

A. Brooks Fischer does not have an updated list tonight.  He states that he needs to get it to O&G with the issues that have been resolved.  He will have it emailed to Jack Healy, Chair tomorrow.  He states that he believes that there are issues that have been taken off the list since last time.  William J. Buckley, Jr. states that the heard from Stacie Kavle and that she wants to know if the soffit issue has been resolved.  Jack Healy, Chair states that Stacie Kavle will continue to pursue the soffit issue.   William J. Buckley, Jr. states that Stacie would like to have a meeting with O&G, the architect and the contractor to try to resolve this because if this is left the way it is, then a credit should be issued for the difference in the design.  Jack Healy, Chair will send her an email.  William J. Buckley, Jr. states that he does feel that it probably involved less work and workmanship so a credit change order should be issued.  He also states that there is no documentation other than the letter from the contractor about this issue and that is unfortunate.  Further discussion ensued.  William J. Buckley, Jr. feels that now there should be a meeting to resolve this issue and the decision should be documented so the Committee can move on.

 

 

Parking Lot Update (Jeff Zullo & Bill Buckley)

Jack Healy, Chair wants to know if the Committee authorized CCA to move forward at the last meeting.  The minutes of the last meeting were reviewed.  He stated that the zoning officer has contacted Leo Paul, First Selectman and Dom Vita, Superintendent and that the cars will have to be moved permanently from Constitution Way within a reasonable time. Jack Healy, Chair will give Ron George a call to see about the proposal tomorrow.

 

 

Motion:  William J. Buckley, Jr., moved to authorize the Chairman to authorize CCA to proceed with the updated design provided that it does not exceed $5,000.00.

So moved.  Seconded:  Bob Blazek

Discussion:  none.

Vote:

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None

All ayes

Motion passed.

 

 

Jack Healy, Chair states that Ron George did get the official letter from P&Z.  Jack Healy, Chair will get it to the members of the Committee.  Jack Healy, Chair states that this is for the parking lot that was approved and not for the extra spaces.

 

Jack Healy, Chair asks George Graikoski to get some housekeeping done of the entire site because he is tired of getting emails about debris.  William J. Buckley, Jr. feels that the lawn in the courtyard is not acceptable to him.  William J. Buckley, Jr. would like to see the revised drawing of the parking lot before next meeting.  Jack Healy, Chair will talk to Ron about getting this done quickly.

 

 

 

Alternative Options List Review (Lynn Chapman)

William J. Buckley, Jr. states that he thought the Committee had requested prices of items that the school has on their priority list so if there is money left, they can address these items.  William J. Buckley, Jr. states that his priority list would include the parking lot and some painting in the bathrooms that are not new.  Lynn Chapman asks that George Graikoski get a proposal for painting and partitions and a separate price for the replacement of the sinks and a vanities for all bathrooms that are not new.  She agrees that all the old bathrooms need to be redone.  William J. Buckley, Jr. wants a list of the bathrooms with the price so it is clear which ones are being done.  Bob Blazek wants to know when the painting of the cafeteria for the Intermediate School will be finished.  George Graikoski states that it will be done.  Peg Perusse states that she has a price for the security system and that they are concerned about the security system especially because the interior courtyard doors have to remain open.

 

 

 

Maintenance Building

Peg Perusse states that if the maintenance building is on campus and part of the project it is reimbursable by the State.   William J. Buckley, Jr. states that he was at the Capital Improvement Committee meeting last night and that it was voted down.  He states that they think that the Building Committee should do it as part of their project.

 

 

6.  FINANCE COMMITTEE – Take actions as needed

 

 

Soft Cost Budget (Jeff Zullo & O&G)

None discussed.

 

 

Finance Committee Report

None discussed.  The Finance Committee did not meet.

 

 

 

Approval of Invoices

 

William J. Buckley, Jr. hands out to the members of the Committee the list of the invoices to be approved and a report entitled, Litchfield Public Schools A/P Aging Summary – All transactions.  Peg and Deb prepared this list that shows bills that have not been paid.  Peg Perusse states that they can not pay them because they have not gotten the signatures from Newman.  William J. Buckley, Jr. again states that Allied is not on this list because they never got the invoices.  Peg Perusse states that she does not get the invoices now until Newman signs them because they had to do a lot of work to get them signed after they were submitted.

 

 

Motion:  William J. Buckley, Jr. moved that the following invoice be forwarded to the Chairman for approval subject to his review of each to make sure that the proper certifications are there.

 

 

VENDOR

 APP/INV#

INV. DATE

 AMOUNT

  SCHOOL

Herbst & Herbst

         883

   11/8/2007

   $603.00

Middle/High

Herbst & Herbst

         883

   11/8/2007

   $297.00

Intermediate

                                       

                                                                Total of $900.00           

So moved.    Seconded: Kent Gilyard

Discussion:  none

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None.

All Ayes

Motion passed.

 

Jack Healy, Chair states that this bill has been entirely brought upon because of the issue of the parking lot.  William J. Buckley, Jr. states that this is because somebody filed an appeal before the wrong agency and that the course was really a legal appeal and that their time limit has now expired so there should not be anymore legal bills for this issue.  Kent Gilyard states that three months ago he stated that this appeal was not legal and that it cost the project money that could have been spent elsewhere.  Jack Healy, Chair states that Peter Herbst did an excellent job.  The Committee agrees.

 

 

Motion:  William J. Buckley, Jr. moved that the following invoice be forwarded to the Chairman for approval for a total amount of $215.90.

 

VENDOR

   APP/ INV#

  INV. DATE

  AMOUNT

SCHOOL

Marianne Arancio Stilson

11122007 -Split

  11/1/2007

    $144.65

Middle/High

Marianne Arancio Stilson

11122007 -Split

  11/1/2007

      $71.25

Intermediate

 

So moved.    Seconded: Kent Gilyard

Discussion:  None.

Vote:

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None.

All Ayes 

Motion passed.

 

 

 

Motion:  William J. Buckley, Jr. moved that the following invoice be forwarded to the Chairman for approval subject to his review of each to make sure that the proper certifications are there.

 

VENDOR

 APP/INV#

INV. DATE

 AMOUNT

  SCHOOL

Herbert S. Newman

      16635

   8/16/2007

 $3,462.50

Intermediate

                           

So moved.    Seconded: Kent Gilyard

Discussion:  Jack Healy, Chair wants to know if this bill brings this to 100%.   William J. Buckley, Jr. states that this invoice has to do with the FFE at the Intermediate School and not the percentage.  

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None.

All Ayes 

Motion passed

 

 

 

Motion:  William J. Buckley, Jr. moved that the Allied Restoration be paid $70,000.00 towards the invoice submitted this evening and that it should be forwarded to the Chairman for approval subject to his review of each to make sure the proper certificates are there and further moved that $7,663.30 be held back in order for the Building Committee to review the work that the Committee is not totally convinced is consistent with the contract.

So moved.    Seconded: Bob Blazek

Discussion:  George Graikoski states that the recommendation was not to pay this bill until the coping issue was resolved. Discussion ensued including the reading of the prior meeting minutes regarding Allied Restoration bills and the bills submitted this evening.  William J. Buckley, Jr. stated that he feels that the Building Committee should hold back some money for a coping issue credit.  William J. Buckley, Jr. states that the entire bill is for $77,663.30 and that the Committee should vote to hold back $7,663.30 to review work that the Building Committee is not convinced has been done totally consistent with the contract. 

Absent: Stacie Kavle, Vice Chair, Jeff Zullo, Mac Bramley, Gary Waugh and Leo Paul - Ex-Officio

Objection:  None.

All Ayes 

Motion passed

 

Jack Healy, Chair will speak to Allied Restoration tomorrow and let them know what the Committee decided this evening.

 

Jack Healy, Chair gives A. Brooks Fischer the list handed out at the beginning of the outstanding invoices and asks him to get them signed and to Peg Perusse immediately.

 

 

7.  TECHNOLOGY UPDATE – TAKE ACTIONS AS NEEDED

 

Peg Perusse states that equipment is being delivered and installed.  She states that there was some issue with the contractor regarding the wiring and that she believes that this has been taken care of.

 

Jack Healy, Chair tells Peg Perusse to get Mike Chadukiewicz to sign the COR’s because they needed to be signed before they were approved.  He states that he d