MINUTES
LITCHFIELD SCHOOL BUILDING COMMITTEE
LITCHFIELD INTERMEDIATE SCHOOL
LIBRARY
SPECIAL MEETING
A
special meeting of the Litchfield School Building Committee was held on
Present
were: R. Blazek, B. Buckley, S. Kavle, M. Bramley, J. Zullo, G. Waugh, J.
Mullen, K. Gilyard.
Also
Present: P. Perusse, D. Knox, BOE
Chairman, BOE members W. Shuhi, F. Simone, D. Falcetti; B. Dranginis,
Selectman, Public and Press.
Meeting
was called to order at
Motion
made by R. Blazek to approve the minutes of the
Motion
Carried. All votes were in the affirmative. M. Bramley
and J. Zullo abstained.
Public
Participation - G. Oneglia,
B.
Dranginis – O&G should be supported as they have integrity and have
financially supported many community activities. There is a lot of mistrust in
the town with negativity toward the completion of the project on time. Ninety-nine percent of O&G projects come
in on time.
K.
Merz, 62 North Street, Secretary of O&G – O&G has a track record for
doing what is right and cited the Westleigh Condominium project of 20 years
ago. When you live in town and have to face the owners years later, when things
don’t go right, O&G steps in and does the right thing.
W.
Shuhi, BOE member – School calendar allows window for construction with the
summer of 2005 as the initial groundbreaking.
Stated that the timeframe was considered when setting BOE calendar.
Communication – G. Waugh said that at the December 9TH BOE
meeting, T. Reardon suggested that no matter who is hired, there should be
interviews with the clients to determine the quality of work and the
sustainability of their projects before finalizing the contract.
J.
Noone – Said he was concerned about residents comparing costs and
reimbursements of Litchfield’s project with
S.
Kavle – mentioned that the reimbursement rate from town to town has nothing to
do with the type of project – it is SDE driven and is district based.
B.
Buckley – The Town said you’ve got $33.0 million and that’s what we’ve got. You
do the best you can do with the cap you have.
G.
Waugh – He informed the BOE members that they had spoken with the architect and
they continue to pursue “Renovate as New”.
BOE wants to get as much as they can with $33.0 million.
B.
Buckley – Our job is challenging. We need to maximize what we get; maximize
reimbursement for the money.
S.
Kavle – Stated that they received a letter from O&G that reiterates what
was said here tonight. Also a letter
from SDE regarding the EDO49RS. Paige Farnham acknowledged receipt of two
EDO49RS stipulating a change in scope, which exceeded the middle/high school
original form. M. Bramley summarized the
letter at S. Kavle’s request and stated that the SDE has some questions that
need responses regarding the square footage differences, the change in scope of
the two projects and will require revisions to the educational
specifications. He also noted that there
is a statement regarding the fact that the Litchfield Middle/High School project
costs are temporarily classified as ineligible due to the large change in scope
and projected costs. He voiced his
concern about moving forward with the project withou having assurance of
funding.
B.
Buckley – Said they have been in the same situation before in
M.
Bramley – Doesn’t think the legislature would turn down but time is a problem,
he is concerned about bringing it back to the town without a definite approval
and there is a concern when combined with issues related to the courthouse.
S.
Kavle – Other towns are in the same position as the process now calls for
funding approval even before a project can be filed with SDE.
J.
Zullo – We have an approved project with approved funds but with modifications.
There is no linkage with the courthouse, this is the State Department of
Education.
P.
Perusse – Stated that this is exactly what David Wedge in the School Facilities
Unit told us to expect. When asked if we
needed to revise Ed Specs or submit anything else along with the ED 049Rs, he
said that we needed to get the ED 049Rs submitted and then they would write a
letter and tell us what else we need.
When Dr. Gibson, J. Healy, C. Miner, A. Roraback and P. Perusse met with
David Wedge earlier in the year, he explained the process and that there
probably wouldn’t be a problem with approval but we had to go through the
process and a change of this magnitude would need be included in the school
construction list and to go back to the General Assembly for approval.
M.
Bramley – Wants to be assured money is in place before a vote.
J.
Zullo – We have an approved project. The State needs to approve a change
request.
M.
Bramley – Wants to ask appropriate legal counsel if the vote can be done
contingent upon funding.
B.
Buckley – School Facilities is in the business of funding school construction,
that’s what they do. Point of
order: Letter should be put in record
and that it be listed on a future agenda for discussion. Also put on future agenda a report from First
Selectman concerning his discussions with the state.
Review
Construction Managers Proposals and take action deemed necessary:
G.
Waugh asked if anyone had prepared an “apples to apples” comparison of the
three proposals. B. Buckley said he had
and said in summary that they all, basically, have the same numbers for all
purposes and the decision may be based on who makes a serious attempt and who
they feel comfortable with. The construction manager and architects must be
able to work together. They, basically, start and end at the same time so any
of the numbers may change to some degree.
B.
Blazek – Asked if it was a correct interpretation of O&G’s comments that
they will do the job for a lump sum and pick up any overages themselves. B. Buckley that said he interpreted it the
same way. J. Healy and S. Kavle have been authorized to negotiate contract and
they will need some lea way for those purposes.
J.
Zullo – One difference is that O&G would be willing to accept a lump sum
contract and take the risk of overruns or incentive to shorten it’s a pretty
good deal.
B.
Blazek – The lump sum is important to lower the risk for the Town with a cap of
$33.0 million. Firm gave them something
to lower the risk to the town, which is good considering the history of the
project. O& G is part of the
community and have done lots in the community.
They have a good record and have come in under budget over and over
again.
B.
Buckley – Said experience has been that construction managers want to do a good
job in towns they reside in and cited
G.
Waugh – Based on presentations it appears that Turner and O&G both had a
large public relations department but not Konover. Thought O&G has
ownership in project and would do a good job as it’s personal to them.
M.
Bramley – Started out with impression that HSNP and O&G would not be right
choice politically. Has since changed his mind and feels HSNP is right choice
and so is O&G. However, they have a challenge and will have to work very
hard. HSNP and O&G will have to assist committee in the process to convince
town.
J.
Mullen – O&G can do the job and be good for the town but burden if no
change. Likes both O&G and HSNP and
said that since they have come to this decision it proves that they were the
best choice the first time around as well.
B.
Buckley – Was looking for a change too. Said he had felt they should distance
themselves and start fresh, but, after going through the process again, he is
comfortable with HSNP and is leaning toward O&G.
K.
Gilyard – Said he is interested in O&G and Turner and would eliminate
Konover for their lack of school experience. Turner and O&G are both good
companies. O&G working in town could
be a benefit. Thought the committee may have a problem with some people in town
because they had chosen the same two.
Thinks they should both come to the table to show the committee what
they would do. Thought all the more reason to go with O&G.
J.
Zullo – In reviewing construction managers, no one can accuse the committee of
not doing due diligence. Committee has
taken a very cautious approach and deep care to review the proposals. In looking at all three proposals and what
they can do, he found Turner’s proposal non-compliant with our request, range
of time seems to be out of kilter and
not clear and would almost consider it not acceptable. It is down to the numbers with the other two
and they are essentially the same. O&G lives in town has offered a fixed
fee, limited risk and incentivizing O&G on their end and will make decision
based on those points.
B.
Blazek – O&G is best for less. Thanked B. Buckley for comparison.
Motion
was made by B. Blazek to authorize J. Healy and S. Kavle to enter into
contract negotiations with O&G to
become the Construction Manager for projects, the contract would be subject to
ratification by Building Committee, sec. by B. Buckley.
Discussion
of amending motion to include language regarding the lump sum but many felt
that it might limit the negotiations at this point. Encouraged members to offer input regarding
what they would like to see in the contract.
B. Buckley, J. Zullo and M. Bramley will be very willing to assist with
details.
B.
Buckley suggested BOE legal counsel review everything after it is put together.
It was resolved that Building Committee would reimburse BOE for attorney
charges. Town attorney may also want to
review. A town resident has also volunteered to review. B. Blazek said that there is a concern regarding
the liability of having an unpaid advisor and Committee should be sure to
communicate with Town regarding legal counsel.
B. Buckley said Leo Paul has attended Building Committee meetings and
has agreed to work with Building Committee.
Motion
was made by M. Bramley to move the question.
Seconded by B. Blazek. Motion
Carried. All votes in affirmative
except B. Buckley and J. Zullo. There
were no abstentions.
Motion
Carried. All votes in affirmative. There were no abstentions.
Motion
was made by M. Bramley to adjourn at
Motion
Carried. All votes were in the affirmative. There were no abstentions.
Respectfully submitted,
Peggy Perusse
Peggy Perusse, Acting
Recording Secretary