Meeting Minutes
LOCATION
DATE OF MEETING
TIME MEETING STARTED
PERSON PREPARING THE MINUTES
Marianne Arancio Stilson
MEMBERS PRESENT
1.
Jack Healy, Chair & BOS Representative
6.
Bob Blazek
2.
William J. Buckley, Jr.
7.
Lynn Chapman
3.
Jeff Zullo, Treasurer & BOF
Representative
8.
Mac Bramley
4. Gary
Waugh - BOE Representative
9.
Kent Gilyard
5.
Stacie Kavle, Vice Chair arrives at
OTHERS PRESENT
George Graikoski of O&G, Jose A. Hernandez & A. Brooks Fischer of Herbert S.
Newman, Tony Crowe, Peg Perusse, Wayne Shuhi & Winnie Harrison
QUORUM PRESENT
Yes
1. CALL TO ORDER
Jack Healy, Chair called the meeting to order at
2. APPROVAL OF MINUTES
Jack Healy, Chair asks for a motion to approve the minutes of the
Motion:
William J. Buckley, Jr. moved to approve the meeting minutes of December
6, 2007.
So moved. Seconded:
Bob Blazek
Discussion:
None
Vote:
Abstention: Gary Waugh and Leo
Paul, Ex-Officio
Deletions/Corrections/Additions:
None
Absent: Stacie Kavle, Vice Chair
All Ayes
Motion passed.
PUBLIC PARTICIPATION
Winnie Harrison comments on the October 4th meeting minutes in regard
to the parking lot, her letter and comments by the Committee.
She discusses credibility.
She also states that she was told today that a wet moldy ceiling tile fell out
of the new boy’s locker room ceiling and on to the floor and doesn’t understand
how this could happen and thinks that the Building Committee should abandon
their fantasy that they can add anything more to the project including the
parking lot until the reasons for having this building project are resolved.
She mentions the media center, heat in the bathrooms, the extra cost for
pizza and the science rooms. She
states that she is concerned. She
states that the Building Committee should not be too proud of the project and
that they need to admit that they can’t afford the parking lot and that they
need to fix the things that need to be fixed first.
Jack Healy, Chair asks Tony Crowe about the ceiling tile issue.
Tony Crowe responds that once the gym is sealed up that one spot will go
away. Jack Healy, Chair asks George
Graikoski if they are working on this.
He states that they are.
4. COMMUNICATION
Report from Jeff Zullo on BOF Communication
Jeff Zullo stated that there was a BOF meeting this month with the new BOF and
that he reported on the status of the project, the contingency and explained
that FFE is built into the contingency figure.
He told them that they were finalizing construction this month and that
all construction would be complete this month.
He told them that they are doing punch listing and incomplete listing and
filing for the certificates of occupancy.
He states that the BOF was very pleased with the continuous effort by the
Committee and there were no major issues or questions from the BOF.
Report from Gary Waugh on BOE Communication
Gary Waugh states that the BOE meeting
was last week and reported about the same things as Jeff Zullo did but the BOE
is concerned about certain facilities not being turned over that are desperately
needed in the school. He states
that they went into an extensive session in which Tony Crowe presented an
updated punch list to the BOE. He
states that many of the original items on the punch list were resolved.
He states that there are some additional items and that they prioritized
them in a 1,2,3 order with 1 as the highest priority and that hopefully that
list will be shared with the Committee members at the next meeting.
He states that in general the BOE is pleased with what has been done and
would like the project brought to closure so they can use the full facility.
Jack Healy, Chair states that so does the Building Committee.
Report from Jack Healy on BOS Communication
Jack Healy, Chair reports that he has given a report to the BOS and used the
figures on George Graikoski’s budget report.
He gave them a status update on the project and reported that the kitchen
is not open yet at the High School.
He also reported on the parking lot and that there was extensive discussion on
that issue. He states that he
told them he did not know how much money would be available to build the parking
lot. He told them that some issues
have come up including sealing all the manholes throughout the school with a
rubber gaskets and that George Graikoski is working on that now and that
$2,000.00 was authorized for that work.
He states that other issues he discussed would be discussed tonight
including fences and gates.
Correspondence
None.
5. ARCHITECT/CONSTRUCTION MANAGER
UPDATES
Jack Healy, Chair states that Leo Paul, Ex-Officio member is here tonight and
that he has to leave to go to another meeting so if the Committee has no
objection, he would like to take the agenda item entitled, Parking Lot Update
(Jeff Zullo and Bill Buckley) out of order.
Motion:
Bob Blazek moved to hear Agenda Item
Parking Lot Update (Jeff Zullo & Bill
Buckley)
So moved.
Seconded: Lynn Chapman
Discussion:
None.
Vote:
Absent: Stacie Kavle, Vice Chair
Objection: None.
All Ayes
Motion Passed.
Parking Lot Update (Jeff Zullo & Bill Buckley)
Bob Blazek discusses the draft drawing of the parking lot as the members of the
Committee look at the drawing. Bob
Blazek states that the only thing missing from the drawing is that there is a
notation on the north side of the parking lot for a twelve foot buffer for trees
and shrubs and that was part of the Planning and Zoning conditions. Jeff Zullo
wants to know about the island area on the drawings and notes the type of trees
noted on the drawing. He would like
to know if the row of trees is being kept there.
Bob Blazek states that it is.
Jeff Healy, Chair states that the drawing note the trees that are in
place now. Bob Blazek states that
it is a total of one hundred and eight spaces.
The drawing is discussed by the members of the Committee.
Discussion of the email from Land Use Administrator, Matt Speck is
discussed including the discussion of the extra thirty spots.
Jack Healy, Chair will check with Matt Speck again on the specific
requirements.
Stacie Kavle arrives at
Jeff Zullo would like input from the Board of Education and the Administration
to find out what their priorities are.
He doesn’t think that the Committee should make these decisions in
isolation. William J. Buckley, Jr.
agrees but adds that the final decision is up to the Building Committee.
He also states that at the Capital Improvement meeting last Wednesday,
they voted to approve a recommendation to the BOS and BOF for $300,000.00 for
the parking lot in the 09/10 fiscal year.
Jeff Zullo and William J. Buckley, Jr. both mention that the advantage of
funding the parking lot through the school project is the forty percent
reimbursement from the State.
Discussion ensued. Jeff Zullo
states that the BOF saw the advantage of doing the parking lot as part of the
school project. He states that
estimates should be gotten over the winter for the parking lot plus the
additional spaces. Bob Blazek
states that the parking lot is a benefit to the community since it is used for
so many community events.
Discussion of the proposed traffic flow changes ensued.
Jack Healy, Chair discusses the fact that the Administration has the
immediate problem of no parking on
Leo Paul, Ex-Officio member leaves.
Jack Healy, Chair states that the real purpose of this meeting tonight was to go
over the budget but because of the number of emails that have been circulated
over the last two weeks it is necessary to formulate a plan on how to go forward
to come to a conclusion on the project.
He states that he spoke to Richard Munday of Herbert Newman and Mike
Brennan at O&G on Monday. He states
that they had a working session last week and they will be having another
working session next Thursday with that he would like a few members of the
Committee there to help make decisions at that meeting.
Jack Healy, Chair states that Jeff Zullo has been working on the budget
and that he has been working on the Building Inspector’s report with HSN and
that other members of the Committee may want to work on other areas of the
project as well to move the project forward.
Discussion ensued about the issues of finances with Cynthia and Jack
Healy, Chair states that he gave her an estimated ending date of the middle of
next year. Mac Bramley wants to
know where they stand on the TCO’s.
Jack Healy, Chair discusses the email from John regarding compliance.
He reported that John is looking for an action plan to get the items
ironed out to get him the certifications that he was looking for.
He states that he did forward that
information on to Newman and O&G.
Jose A. Hernandez speaks to the members of the Committee about the solution to
the TCO compliance issue and states that the discrepancy in the language in the
statement of professional opinion and the provision of the Statutes that relates
to the certificate of occupancy has been worked out and it will be taken care of
by Newman. He states that he is
going issue by issue in each school with John and that the TCO’s and their time
frame are determined by the Building Inspector.
He states that the only issue in the Intermediate School was that the
report that was sent to Newman implied that the fire pump had not been tied into
the fire alarm monitoring system.
George Graikoski states that the form is incorrect because the boxes were not
checked and should have been because it is tied into the system.
He states that they will be coming back next Wednesday to verify and
double check everything and get the correct form.
The pump is discussed.
The issue of the expiration dates of the TCO’s is discussed.
The issue of getting the final CO’s is
discussed. Jack Healy, Chair states that a lot of these issues will be resolved
at next Thursday’s meeting.
Jack Healy, Chair asks for a motion for a temporary recess.
Motion:
Jeff Zullo moved to have a temporary recess.
So moved.
Seconded: Bob Blazek
Discussion:
None.
Vote:
Absent:
Leo Paul, Ex-Officio
Objection: None.
All Ayes
Motion Passed.
Jack Healy, Chair calls the meeting back into session.
Budget (O&G)
George Graikoski of O&G hands out to the members of the Committee the following
reports for the High/Middle School and the Intermediate School:
Monthly Progress Report #14, November
2007; Summary Data, November 2007; Construction Manager’s Monthly Cost Control
Report, November 2007; Change Orders By Trade Contractor, November, 2007;
Project Commentary, November 2007 and Phasing Plans Summer 2007 and September
23rd Schedule.
Jack Zullo states that he sent an email out to all the members of the Committee
this afternoon and that George Graikoski made adjustments to the budgets that
are valid, that he reallocated some of the negative amounts back into the
expended amounts and that they are still carrying forward the $350,000.00
contingency in LIS and $160,000.00 contingency in LHS from the FFE account.
George Graikoski goes over the budget
report in detail including the changes that he made to the report from last
month. Discussion ensued.
The Spectrum line item is discussed and the O&G line item of the report
is also discussed. William J. Buckley,
Jr. is concerned because the invoices are not matching the report and doesn’t
understand why it is not correct.
Jack Healy, Chair wants a report on the change order requests.
Jose A. Hernandez states that Newman has received four hundred and
seventy nine change order requests and has acted on four hundred and forty three
of them and that thirty three need an additional review.
He states that he assigned Brooks A. Fischer to work with Peter Bowman to
address these thirty three. Jack Healy,
Chair wants the process to get done because contractors are contacting him and
he does not want any lawsuits. He
also discusses the fact that he is getting calls about when the punch listing is
going to be done. Jose A. Hernandez
states that the action plan is that Newman will come out and look at the entire
project and make a list. He states
that his company does not want to be perceived as obstructionists and the review
of the COR’s is very serious to them. Jack
Healy, Chair states that Newman is the Committee’s quality control on the
project. Jeff Zullo states that he sent
out an email this morning to the members of the Committee regarding the COR’s
and that George Graikoski stated that there are fifty that have been returned by
Newman for follow up and there are twenty-five that have been approved by HSN
and are awaiting a sign off for pay applications.
Jose A. Hernandez states that Newman has no payment applications in their
office. He states that any pay
applications have either been approved or rejected and sent back to O&G.
A very lengthy discussion ensued between George Graikoski and Jose A.
Hernandez about the missing papers and the procedure that will be followed to
get the CO requests done more efficiently from now on.
George Graikoski states that there are
one hundred and thirteen change orders that can not be accounted for from
Newman. A discussion ensued over merging
Newman and O&G’s lists to see which ones have not yet been approved or received
by Newman to get them done quickly.
A. Brooks Fischer states that they keep a log of all of them.
Jack Healy, Chair wants the two companies’ logs compared and wants them
cross checked by next Wednesday. He
states that this should be a very easy process.
George Graikoski wants Newman to circle the ones that they don’t have and
to have a weekly meeting with Newman to go over these change order requests to
get them done by the end of January and A. Brooks Fischer feels that the
meetings are not necessary to go over all the requests and that the only ones
that should be gone over are the problem ones. Jose
A. Hernandez agrees. George Graikoski
states that having a meeting is easier to come to an agreement and to sign it
right then and there rather than go back and forth with emails and phone calls.
Further discussion ensued.
Jeff Zullo is concerned because Newman says that there are only thirty three and
O&G says that there are one hundred and thirteen. He states that both companies
have to come to an agreement on the process and to get this done quickly.
After this discussion between the two companies, no resolution occurred.
William J. Buckley, Jr. is upset that so much time has been taken this
evening between the two companies and feels that they should come to a
compromise and get this comparison and the change orders done.
He states that this work should be done by the end of December and that
both companies are highly paid and that this issue should be resolved.
Jose A. Hernandez states that there are a number of change orders that
can be resolved without a meeting.
Jack Healy, Chair orders that the process is defined by next Wednesday and that
he wants all the COR’s processed by the January 17th meeting.
William J. Buckley, Jr. feels that a
month is too long and that he has no confidence that this will be done.
Jack Healy, Chair will talk about having a special meeting at next
Thursday’s workshop meeting.
Peg Perusse has a report entitled Soft Costs –
Jeff Zullo mentions the issue with the safety gate for the stairwell and the
ramps at the high school and is upset that the Building Committee is only
finding out about this issue now and that these issues have never been on the
issue list. He states that he feels
that Newman has condoned what is being built by not communicating with the
Building Committee and that their silence is concurrence with the construction
as built. Jose A. Hernandez states
that the gate is a building inspector issue.
Jeff Zullo is upset that at this late date he is hearing about issues
that have never come up before.
A. Brooks Fischer states that they have been battling the gate issue with
O&G for over a year now. Some of
the members of the Building Committee state that they were aware of this issue.
William J. Buckley, Jr. leaves at
Jose A. Hernandez states that William J. Buckley, Jr. is correct and that there
are going to be issues that O&G will be advocating the contractor’s costs and
that Newman will not be agreeing with that and that Newman will be coming back
to the Building Committee with their recommendations.
Further discussion ensued.
Gary Waugh is very concerned that there is no accountability for Newman’s
mistakes and that they have not taken ownership for the resolutions of the costs
and sites the counters in the library as an example.
He feels that Newman has to take responsibility for their errors and has
seen the opposite of that throughout this entire project.
He states that he is tired of the Building Committee having to pay for
errors by Newman. Jose A. Hernandez
states that he will take his comments back to Richard Munday and that this can
be discussed next Thursday. Jack
Healy, Chair will talk to Richard Munday about this issue.
Schedule Update (O&G)
Jack Healy, Chair states that there will be a meeting next week on the schedule
of the project. The TCO for the
media center is discussed. Jose A.
Hernandez states that as soon as they get the corrected report from O&G it will
go right to John Worthington with their letter.
They are waiting for a TCO.
Wall Panel Update (O&G and HSN)
George Graikoski states that he spoke to Allied and this will be completed by
the end of January.
LHS Ceiling Replacement, Noise Attenuation and Noise Levels (HSN)
George Graikoski reports that the tile and the materials are in and Gar-San is
scheduled to start the work within two weeks.
Gary Waugh states that it would be easier for everyone if the work could
be finished while the students are out for the holiday break. George Graikoski
will talk to Ernie and Gar-San.
Credit Update (O&G)
None discussed.
Issues List Review (HSN)
A. Brooks Fischer states that it is ongoing and will send another one out to O&G
for their mock-up.
Jack Healy, Chair discusses the fact that the ventilators are not working.
George Graikoski states that they are not working the way they should be
working and that there is a meeting on Thursday with the Vice President of Titan
Mechanical to resolve this issue.
George Graikoski discusses the procedure for getting this resolved next week.
Peg Perusse states that there is a problem with the insulation in the
Alternative Options List Review (Lynn Chapman)
None discussed.
None discussed.
6. FINANCE COMMITTEE – Take actions
as needed
Soft Cost Budget (Jeff Zullo & O&G)
None discussed.
Finance Committee Report
None discussed. The Finance
Committee did not meet.
Approval of Invoices
Jeff Zullo hands out to the members of the Committee the list of the invoices to
be approved.
Motion:
Jeff Zullo moved that the following invoices be forwarded to the Chairman
for approval subject to his review of each to make sure that the proper
certifications are there.
|
VENDOR |
APP/INV# |
INV. DATE |
AMOUNT |
SCHOOL |
|
Allied Restoration |
14 |
|
$7,663.00 |
Middle/High |
|
Gar-San |
21-Split |
|
$104,315.36 – |
Middle/High |
|
General Welding |
16 |
|
$2,080.50 |
Middle/High |
|
Kennedy Electric |
22 |
|
$29,840.45 |
Middle/High |
|
M.J. Daly |
19 |
|
$3,876.00 |
Middle/High |
|
R&R Windows |
12 |
|
$44,336.50 |
Middle/High |
So moved. Seconded:
Kent Gilyard
Discussion:
R&R Windows is discussed.
Absent: William J. Buckley, Jr. &
Leo Paul - Ex-Officio
Abstention: Jack Healy, Chair and Mac Bramley
Objection: None.
All Ayes
Motion passed.
Motion:
Jeff Zullo moved that the following invoices be forwarded to the Chairman
for approval subject to his review of each to make sure that the proper
certifications are there.
|
VENDOR |
APP/INV# |
INV. DATE |
AMOUNT |
SCHOOL |
|
General Welding |
14 |
|
$26,828.00 |
Intermediate |
|
Gar-San |
21- |
|
$30,139.70 |
Intermediate |
So moved. Seconded:
Kent Gilyard
Discussion:
None.
Absent: William J. Buckley, Jr. and
Leo Paul - Ex-Officio
Abstention: Mac Bramley
Objection: None.
All Ayes
Motion passed.
Motion:
Jeff Zullo moved that the following invoice be forwarded to the Chairman
for approval for a total amount of $271.60.
|
VENDOR |
APP/ INV# |
INV. DATE |
AMOUNT |